Rural Solar Electrification Project

Site terracing, construction, installation, and pole distribution for rural solar electrification with HUAWEI.

HUAWEI Cameroon Jun 1, 2020 — Sep 30, 2021
Overview

About the project

Delivered for HUAWEI under the Ministry of Water and Energy, this rural electrification programme brought solar power to communities across Cameroon. Evergreen's scope was end-to-end: site terracing and civil construction to prepare each location, solar installation, and the distribution and erection of poles to carry power into the communities. It is the kind of work that sits squarely in our mission — sustainable energy infrastructure that uplifts the communities it reaches.

HUAWEI
Client
Min. Water & Energy
Authority
Turnkey
Scope
Cameroon
Country
The work

Challenge, solution, outcome

Challenge

Rural electrification means working across dispersed sites with limited existing infrastructure — every location needs ground preparation before any solar equipment can be installed.

Solution

We self-performed the full chain — terracing and civil works, then solar installation, then pole distribution — so each site moved from raw ground to live power under one coordinated team.

Outcome

Communities across the programme connected to clean solar power, delivered for HUAWEI and the Ministry of Water and Energy.

Delivery

Project timeline

  1. Site terracing

    Completed

    Jun 1, 2020 — Oct 31, 2020

    Ground preparation and terracing across the project sites.

  2. Civil construction

    Completed

    Sep 1, 2020 — Feb 28, 2021

    Civil works to prepare each location for installation.

  3. Solar installation

    Completed

    Jan 1, 2021 — Jun 30, 2021

    Installation of solar systems across the programme.

  4. Pole distribution & connection

    Completed

    Apr 1, 2021 — Sep 30, 2021

    Distribution and erection of poles and community connection.

The team

Who delivered it

EK

Emmanuel Kondé

Renewable Energy Lead

Solar PV systems engineer.

BN

Bertrand Njoya

Site Operations Manager

Coordinated multi-site civil and installation works.

Partners

With

HUAWEIMinistry of Water and Energy

Tags

Solar Rural electrification Civil works HUAWEI