225 kV Power Transmission Line

Pole distribution, erection, and cabling for a high-tension transmission line across East and West Cameroon.

KALPATARU East & West Regions, Cameroon Mar 1, 2021 — Aug 31, 2022
Overview

About the project

Evergreen was engaged on one of Cameroon's major high-tension projects: the 225 kV power transmission line spanning the East and West regions. Working under KALPATARU on behalf of the Cameroon Government, our crews handled pole distribution, tower and pole erection, and cable installation across long, often remote stretches of the route. High-tension transmission demands exacting standards of safety and quality — every span surveyed, every structure erected to specification, every conductor strung and sagged to tolerance.

225kV
Line voltage
2
Regions
KALPATARU
Client
Govt.
Authority
The work

Challenge, solution, outcome

Challenge

A high-tension transmission line crossing two regions means long, dispersed worksites, demanding logistics for poles and conductors, and zero tolerance for safety or quality lapses on energised infrastructure.

Solution

We staged pole and conductor distribution against the construction sequence, coordinated access along the route, and held a strict erection-and-stringing quality regime backed by our safety standards.

Outcome

Delivered our scope of the 225 kV line across the East and West regions to specification — a piece of national grid infrastructure built to serve for decades.

Delivery

Project timeline

  1. Survey & mobilisation

    Completed

    Mar 1, 2021 — May 31, 2021

    Route survey, access coordination, and site mobilisation across the corridor.

  2. Pole & tower distribution

    Completed

    Jun 1, 2021 — Nov 30, 2021

    Distribution and staging of poles and towers along the route.

  3. Erection

    Completed

    Sep 1, 2021 — Apr 30, 2022

    Erection of poles and towers to specification.

  4. Stringing & commissioning

    Completed

    Mar 1, 2022 — Aug 31, 2022

    Conductor stringing, sagging, and handover of the completed sections.

The team

Who delivered it

PM

Patrick Mbah

Project Lead

Heads electrical works; LV/MV and high-tension specialist.

MF

Mewoabi Fritz

Executive Sponsor

CEO & Managing Director.

Partners

With

KALPATARUCameroon Government

Tags

High-tension Transmission Government Grid
Gallery

On site

Images and video from the project.

Have a project like this?

Tell us your scope and timeline — a senior lead will respond within one business day.