Evergreen Regional Supply Hub
A 12,000 m² distribution centre stocking 5,000+ SKUs with same-day dispatch.
About the project
A purpose-built logistics center stocking 5,000+ SKUs with same-day dispatch across the region, equipped with rooftop solar offsetting 60% of operations.
Challenge, solution, outcome
Challenge
Standing up a regional distribution capability meant building and operationalising a large warehouse while keeping running costs sustainable.
Solution
We self-performed the build, installed rooftop solar to offset operating energy, and designed the racking and loading layout around same-day dispatch.
Outcome
The hub now stocks 5,000+ SKUs with same-day dispatch and a 96% on-time delivery rate, with rooftop solar offsetting 60% of operations.
Project timeline
Design & groundworks
CompletedSep 1, 2023 — Dec 20, 2023
Warehouse design, site works, and foundations.
Structure & envelope
CompletedDec 21, 2023 — Apr 30, 2024
Steel structure, cladding, and roofing.
Fit-out & solar
CompletedMay 1, 2024 — Jul 31, 2024
Racking, loading bays, and rooftop solar installation.
Commissioning
CompletedAug 1, 2024 — Aug 15, 2024
Warehouse management setup and operational go-live.
Who delivered it
Sarah Mbella
Head of Supply Services
Procurement and logistics lead.
Emmanuel Kondé
Solar Lead
Designed the rooftop solar offset.
With
Tags
On site
Images and video from the project.